Leisure, Arts And Communities Committee - 14/09/2009

At a MEETING of the LEISURE, ARTS AND COMMUNITIES COMMITTEE held at Dundee on 14th September, 2009.

 

Present:-

 

Lord Provost John R LETFORD

 

 

 

BAILIES

 

Willie SAWERS

Helen WRIGHT

Roderick A J WALLACE

George REGAN

 

Derek J SCOTT

 

COUNCILLORS

 

Ken GUILD

Stewart HUNTER

Laurie BIDWELL

Jim BARRIE

Ken LYNN

Tom FERGUSON

Jimmy BLACK

Craig MELVILLE

Brian GORDON

Andrew DAWSON

Christina ROBERTS

Richard McCREADY

Will DAWSON

Alan G ROSS

Donald HAY

Bob DUNCAN

Kevin KEENAN

Elizabeth F FORDYCE

 

Mohammed ASIF

 

 

Councillor Bob DUNCAN, Convener, in the Chair.

 

The minute of meeting of this Committee of 24th August, 2009 was held as read.

 

Unless marked thus * all items stand delegated.

 

I CAIRD PARK STADIUM - REPLACEMENT HAMMER CAGE

 

There was submitted Agenda Note AN191-2009, whereby it was reported that in order to enhance the rating of the stadium to hold events, a replacement hammer cage was required to be supplied and installed. This would include the removal of the existing cage which did not meet the recognised standards of the UK Athletics. The new cage would be to the appropriate specification which would encourage more use of the facility.

 

Dundee City Council approached three specialist suppliers to have these works carried out: detailed below were the estimates obtained:-

 

Newff Athletic Equipment Ltd

20,585

 

Pro Athletics Ltd

18,485

 

Stadia Sports Supplies - did not quote.

 

The cost of these works could be met from the Quality of Life budget for 2009/2010.

 

The Committee approved the above works and awarded the replacement hammer cage to Pro Athletics.

 

II SERVICE LEVEL AGREEMENTS WITH DUNDEE COLLEGE, CRAIGOWL COMMUNITIES AND CM ASSOCIATES 2008/2011 AND PROGRESS OF LITERACYSINITIATIVE

 

There was submitted Report No 441-2009 by the Director of Leisure and Communities, informing the Committee of the progress of the Literacy's Partnership in 2008/2009 and updating the Committee on the Service Level Agreements with Dundee College, Craigowl Communities and CM Associates for the period 2008/2009 as approved in Report No 123-2008.

 

The Committee agreed to:-

 

(i)                                         acknowledge and progress the key achievements of the Partnership during 2008/2009; and

 

(ii) approve that an annual payment for the period 2009/2010 of 39,000 be made by Dundee City Council to Dundee College, 32,000 to Craigowl Communities and 14,000 to CM Associates upon satisfactory provision of the service specifications. The caveat on this would be that the money would be released on a quarterly basis and if targets were not being achieved then the payments would be reviewed and adjusted accordingly.

 

III TENDERS RECEIVED

 

There was submitted Report No 458-2009 by the City Architectural Services Officer detailing tenders received in respect of Lynch Sports Centre - Lighting Suspension Hooks.

 

The Committee agreed to accept the lowest offer from E W Edwardson (Electrical Contractors) Ltd in the sum of 6,050 including allowances of 1,750 for nightshift working and 970 for professional services, giving a total expenditure of 8,770.

 

IV CAMPERDOWN PARK - CAFE/VISITOR/EDUCATION CENTRE

 

There was submitted Report No 454-2009 by the Director of Leisure and Communities and City Architectural Services Officer, detailing the tenders received in respect of the Camperdown Park Cafe/Visitor/Education Centre and requesting a decision on acceptance thereof.

 

The Committee agreed that approval be given for the acceptance of the agreed maximum price submitted by Dundee Contract Services in the amount of 850,000 and also for allowances amounting to 160,000, giving a total cost of 1,010,000.

 

 

 

 

Bob DUNCAN, Convener.