City Development Committee - 09/05/2005
At a MEETING of the PLANNING AND TRANSPORTATION COMMITTEE held at Dundee on 9th May 2005.
Present:-
Lord Provost John R LETFORD |
|
|
BAILIES
C D P FARQUHAR |
John CORRIGAN |
Bruce D MACKIE |
|
Ian BORTHWICK |
|
COUNCILLORS
Jill SHIMI |
Helen DICK |
Christina ROBERTS |
Kevin KEENAN |
Nigel DON |
Will DAWSON |
Fiona M GRANT |
Bob DUNCAN |
Elizabeth F FORDYCE |
Christopher HIND |
Andrew DAWSON |
Roderick A J WALLACE |
Joe MORROW |
Willie W SAWERS |
Charles A WEBSTER |
Fraser MACPHERSON |
Joe FITZPATRICK |
Derek J SCOTT |
Councillor Fiona GRANT, Convener, in the Chair.
The minute of meeting of this Committee of 18th April 2005 was held as read.
Unless marked thus * all items stand delegated.
I CENTRAL WATERFRONT - TENDERS RECEIVED BY CITY ENGINEER
There was submitted Report No 213-2005 by the City Engineer detailing offers received in respect of Dundee Central Waterfront - Dock Street Tunnel Strengthening (Partnering Contractor).
The Committee agreed that:-
(i) the City Engineer instruct the preferred contractor, AMCO, to carry out advanced investigations and work with the design team to develop the detailed proposals and incur costs up to a value of 100,000 with a view to establishing the Agreed Maximum Price (AMP);
(ii) the Director of Planning and Transportation negotiate a contract within the overall allowance of 8.495 million; the contract will be under a partnering arrangement with AMCO on the basis of the submitted tender and following the finalisation of the detailed design and AMP; and
(iii) the Depute Chief Executive (Support Services) be authorised to accept the offer recommended by the Director of Planning and Transportation.
FIONA GRANT, Convener.