Education Committee - 26/11/2007

At a MEETING of the EDUCATION COMMITTEE held at Dundee on 26th November, 2007.

 

Present:-

 

Lord Provost John R LETFORD

 

 

 

BAILIES

 

George REGAN

Roderick A J WALLACE

Derek J SCOTT

Helen WRIGHT

 

Ian BORTHWICK

 

COUNCILLORS

 

Kevin KEENAN

Helen DICK

Stewart HUNTER

Mohammed ASIF

Ken GUILD

Ken LYNN

Laurie BIDWELL

Jim BARRIE

Alan ROSS

Tom FERGUSON

Jimmy BLACK

Donald HAY

Brian GORDON

David BOWES

Rev J WILSON

Richard McCREADY

Andrew DAWSON

Mr M CHOHAN

Joe MORROW

Will DAWSON

Mr E BAILLIE

Fraser MACPHERSON

Bob DUNCAN

Mrs H MILLAR

 

Elizabeth F FORDYCE

 

 

Councillor Laurie BIDWELL, Convener, in the Chair.

 

The minute of meeting of this Committee of 22nd October, 2007 was held as read.

 

Unless marked thus * all items stand delegated.

 

I HM INSPECTORATE OF EDUCATION - ST JOSEPH'S RC PRIMARY SCHOOL

 

There was submitted and noted report relative to the above.

 

II TENDERS RECEIVED - OFFICER APPROVAL

 

There was submitted for information Agenda Note AN277-2007 noting that due to timescales involved, the Director of Education and City Architectural Services Officer in consultation with the Education Convener and Group spokespersons, agreed that the following works be carried out:-

 

(i) ROCKWELL SECONDARY SCHOOL - ADDITIONAL EMERGENCY LIGHTING

 

Awarded to Jaydee Heating and Electrical, Dundee under a partnering project for 11,864.81, together with allowances of 2,000 for minor decoration work, and 1,130 for professional services, making a total expenditure of 14,994.81.

 

The Committee noted the above.

 

III TEACHER REPRESENTATION ON THE EDUCATION COMMITTEE

 

There was submitted Agenda Note AN278-2007 whereby reference was made to Article XI of the minute of meeting of the Statutory Meeting of the City Council of 24th May, 2007, wherein it was agreed that the current teacher representatives continued for a further period of six months to allow arrangements to be made for new representatives to be appointed to the Committee.

 

Three nominations were received and following a ballot of all teachers, the following candidates were successful:-

 

Mr Eric Baillie

Mrs Helene Millar

The Committee agreed that above-named persons be appointed as members of the Education Committee with immediate effect.

 

IV SCHOOL TERMS AND HOLIDAYS 2008/2009

 

There was submitted Report No 534-2007 by the Director of Education seeking approval for school terms and holidays for Session 2008/2009.

 

The Committee agreed the school terms and holidays for Session 2008/2009 as detailed in the report noted below:-

 

SCHOOL TERMS AND HOLIDAYS 2008/2009

IN SERVICE

DAYS

PUPIL SCHOOL

DAYS

Autumn

Start

Staff

Monday, 18th August, 2008

Day 1

 

Term

 

Pupils

Tuesday, 19th August, 2008

 

 

 

End

 

Friday, 3rd October, 2008

 

34

 

 

 

 

 

 

Autumn

Start

 

Monday, 6th October, 2008

 

 

Holiday

End

 

Friday, 17th October, 2008

 

 

 

 

 

(10 school days)

 

 

 

 

 

 

 

 

Winter

Start

 

Monday, 20th October, 2008

 

 

Term

 

 

Thursday, 13th November, 2008

Day 2

 

 

 

 

Friday, 14th November, 2008

Day 3

 

 

End

 

Tuesday, 23rd December, 2008

 

45

 

 

 

 

 

 

Christmas

Start

 

Wednesday, 24th December, 2008

 

 

Holiday

End

 

Tuesday, 6th January, 2009

 

 

 

 

 

(10 school days)

 

 

 

 

 

 

 

 

Spring

Start

 

Wednesday, 7th January, 2009

 

 

 

 

 

By Cluster February/March, 2009

Day 4

 

 

 

 

Fri/Mon, 13th/16th February, 2009

Mid Term

 

 

End

 

Friday, 3rd April, 2009

 

60

 

 

 

 

 

 

Spring

Start

 

Monday, 6th April, 2009

 

 

Holiday

End

 

Friday, 17th April, 2009

 

 

 

 

 

(10 school days)

 

 

 

 

 

 

 

 

Summer

Start

 

Monday, 20th April, 2009

 

 

Term

 

 

Monday, 4th May, 2009

May Day

 

 

 

 

 

Friday, 22nd May, 2009

Day 5

51

 

 

 

Monday, 25th May, 2009

Victoria Day

 

 

 

End

 

Thursday, 2nd July, 2009

 

 

 

 

 

TOTAL

 

190

 

Total Number of School Days for Pupils

190

Total Number of Working Days for Staff

195

Session

Start

Staff

Monday, 17th August, 2009

 

 

Pupils

Tuesday, 18th August, 2009

Notes: Easter Sunday, 12th April, 2009

Induction Days for Primary 7 children will be agreed by clusters in June 2009

Commencement of SQA Examination Tuesday, 5th May, 2009 (subject to confirmation)

 

V DUNDEE SCHOOLS PPP PROJECT

 

Councillor McCready declared a non-financial interest by virtue of his wife being a member of staff at St Saviour's R C High School.

 

There was submitted Report No 591-2007 by the Director of Education advising the Committee as to progress on the construction of the schools in Phase 1 of the PPP Project.

 

The Committee noted:-

 

(i) the anticipated construction completion dates for the schools in Phase 1 of the PPP Project;

 

(ii) that detailed programmes had been developed for schools in Phase 1 of the PPP Project covering Fitting-Out and Decant of Schools, Curriculum Matching and School Staffing Arrangements; and

 

(iii) that the programmes may require to be modified to reflect any movement in Discovery Education plc's anticipated construction completion dates.

 

VI SUPPORTING LEARNING IN DUNDEE

 

There was submitted Report No 596-2007 by the Director of Education seeking Committee approval for the Education Department's revised policy on Supporting Learning in Dundee.

 

The Committee agreed the revised Policy on Supporting Learning in Dundee as detailed in the report.

 

VII DISABILITY EQUALITY SCHEME 2007/2010 - PROGRESS REPORT

 

There was submitted Report No 597-2007 by the Director of Education informing the Committee of the progress made in implementing the Education Department's Disability Equality Scheme 2007/2010.

 

The Committee noted the progress made in applying the Education Department's Disability Equality Scheme 2007/2010 and approved the Department's Disability Equality Scheme 2007/2010: Annual Report November 2007.

 

VIII TENDERS RECEIVED

 

There was submitted Report No 607-2007 by the City Architectural Services Officer detailing tenders received and requesting a decision thereon:-

 

(i) ST MARY'S RC PRIMARY SCHOOL - WATER INGRESS TREATMENT

 

The Committee agreed to accept the offer by Raynor Roofing Ltd, Dundee of 20,441.50, together with an allowance of 2,913 for professional services, making a total expenditure of 23,354.50.

 

The Committee noted that Raynor Roofing Ltd, Dundee had listed the undernoted sub-contractor:-

 

AT Roberts - Water Ingress Treatment.

 

 

 

 

Laurie BIDWELL, Convener.