Policy And Resources Committee - 08/11/2010

At a MEETING of the POLICY AND RESOURCES COMMITTEE held at Dundee on 8th November, 2010.

 

Present:-

 

Lord Provost John R LETFORD

 

 

 

Depute Lord Provost Ian BORTHWICK

 

 

 

BAILIES

 

Willie SAWERS

Helen WRIGHT

Derek J SCOTT

 

Roderick A J WALLACE

 

 

COUNCILLORS

 

Ken GUILD

Elizabeth F FORDYCE

Laurie BIDWELL

Jim BARRIE

Stewart HUNTER

Tom FERGUSON

Jimmy BLACK

Craig MELVILLE

Brian GORDON

David BOWES

Christina ROBERTS

Richard McCREADY

Andrew DAWSON

Alan G ROSS

Donald HAY

Will DAWSON

Kevin KEENAN

Fraser MACPHERSON

Bob DUNCAN

Mohammed ASIF

Helen DICK

 

Councillor Ken GUILD, Convener, in the Chair.

 

The minute of meeting of this Committee of 25th October, 2010 was held as read.

 

Unless marked thus * all items stand delegated.

 

I REVENUE MONITORING 2010/2011

 

There was submitted Report No 648-2010 by the Director of Finance, providing the Committee with an analysis of the 2010/2011 Projected Revenue Outturn as at 30th September, 2010 monitored against the adjusted 2010/2011 Revenue Budget.

 

The Committee:-

 

(i) noted that the overall General Fund 2010/2011 Projected Revenue Outturn as at 30th September, 2010 showed an overspend of 542,000 against the adjusted 2010/2011 Revenue Budget;

 

(ii) noted that the Housing Revenue Account as at 30th September, 2010 was projecting a breakeven position against the adjusted HRA 2010/2011 Revenue Budget;

 

(iii) instructed the Director of Finance to take every reasonable action to ensure that the 2010/2011 revenue expenditure was below or in line with the adjusted Revenue Budget;

 

(iv) instructed the Director of Finance in conjunction with all Chief Officers of the Council to continue to monitor the Council's 2010/2011 Projected Revenue Outturn.

 

II CAPITAL EXPENDITURE MONITORING 2010/2011

 

There was submitted Report No 637-2010 by the Director of Finance appraising members of the latest position regarding the Council's Capital Expenditure Programme 2010/2011.

 

The Committee noted the contents of the report.

 

III DUNDEE COMMUNITY REGENERATION FUND 2010/2011 - 2012/2013

 

There was submitted Report No 654-2010 by the Assistant Chief Executive relative to the above.

 

The Committee approved the funding process and the proposals contained in Section 5 of the report appended hereto (Appendix I).

 

IV TELEPHONY INFRASTRUCTURE UPGRADE

 

There was submitted Report No 650-2010 by the Head of Information Technology detailing tenders received for a major upgrade to the Council's telephony infrastructure and outlining the requirement for this investment and upgrade.

 

The Committee:-

 

(i) approved the acceptance of the OGC Buying Solutions tender of 390,100 from Freedom Communications (UK) Ltd, for the upgrade detailed in the report; and

 

(ii) remitted to the Head of Information Technology to develop a project plan and migration plan to manage the project.

 

V INSTALLATION OF AUTOMATIC METER READING TECHNOLOGY

 

After considering Report No 655-2010 by the City Architectural Services Officer relative to the above, the Committee authorised the Director of Finance to enter into a Buying Solution Framework Agreement with Stark Software International Ltd, Horley on the undernoted basis:-

 

Stark International Ltd, Horley

65,907

Allowance for Professional Services

16,500

 

Total

82,407

 

Projected Revenue Costs (over 5 year period)

78,320

 

VI NEW OLYMPIA AND ALLAN STREET CAR PARK

 

Councillors Duncan, Ross, Hunter, McCready and Bailie Wallace declared a non-financial interest in this item by virtue of being the Council's representatives on Dundee Leisure.

 

After considering Report No 660-2010 by the Director of Leisure and Communities, Director of City Development and City Architectural Services Officer detailing tenders received for the above, the Committee agreed to accept the tender submission from Mansell Construction Services Ltd, Perth amounting to 24,113,904.52, together with the undernoted allowances amounting to 7,347,000, giving a total cost of 31,460,904.52.

 

 

Several Works - Construction of Pool and Car Park

 

24,113,904.52

Allowances for:-

 

Provision of Eastbound Bus Shelter

Works to East Whale Lane (South)

Works to South Car Park

Road Traffic Assessment Works

Pedestrian Access to Gallagher's Retail Park

Archaeology Works

Provision of Client Telephones

Kitchen/Cafe Fit-Out

Flumes Enhancement

Feature Lighting

Automatic Doors (draught lobby)

Pool Equipment

Loose Furniture and Equipment

Sundry Client Fit-Out Items

Public Art (1%)

Thermal Modelling

Building Warrant

Planning Fee

Construction (Design and Management) Co-ordinator

Professional and Specialist Consultancy Services

Contingences

 

 

15,000

250,000

100,000

100,000

50,000

50,000

20,000

135,000

220,000

100,000

75,000

100,000

150,000

100,000

250,000

20,000

76,000

15,000

38,000

3,483,000

2,000,000

 

Total

7,347,000

7,347,000.00

Total Project Cost

 

31,460,904.52

 

The Committee noted that the following sub-contractors would be used by Mansell Construction Services Ltd:-

 

TRADE

SUB-CONTRACTOR

LOCATION

 

Ground Consolidation and Piling Work

BBGE (Balfour Beatty) Ltd

Glasgow

Groundwork, Excavation

BBCE (Balfour Beatty) Ltd

Aberdeen

Steelwork

RIM Fabrications

Inverurie

Concrete Work

Realm Construction Ltd

Lochgelly

Glazing

Esk Glazing

Montrose

Metalwork

Fenwick Ltd

Dundee

Lift Installation

Kone Lifts plc

Edinburgh

WC Cubicles

Lamart

Dundee

Mechanical Installation

BBES (Balfour Beatty) Ltd

Glasgow

Electrical Installation

BBES (Balfour Beatty) Ltd

Glasgow

Render Work

Muirfield Contracts Ltd

Dundee

Roller Shutters

Aable Doors Ltd

Dundee

Waterproof Render

Quickseal Ltd

Glasgow

Stone Cladding

Stirling Stone Ltd

Stirling

Reception Fitments

Bentleys Ltd

Dundee

Precast Concrete Stairs

Creagh Concrete Products Ltd

Edinburgh

Flooring

McGregor Flooring

Glasgow

Bird Control

Richardson & Starling Ltd

Dundee

Painter

AT Roberts

Dundee

 

VII QUALIFYING LEVELS FOR WORKING FAMILIES TAX CREDIT AND COUNCIL EMPLOYEES

 

It was reported that this item had been placed on the agenda by Councillor Bidwell.

 

The Committee approved the undernoted resolution.

 

This Committee instructs the Chief Executive to undertake a review to ascertain the number of Council employees potentially affected by changes in Tax Credits, as announced by the Chancellor of the Exchequer in his June 2010 Budget and the October 2010 Comprehensive Spending Review. This review should focus particularly, but not exclusively, on the increase in the minimum hours threshold for qualifying for Working Families Tax Credits.

 

Furthermore, the Council explores ways it might mitigate the negative effect of these changes on its employees to be disqualified from Tax Credits when the qualifying conditions change.

 

Finally, that the Chief Executive reports back to the Policy and Resources Committee.

 

The Committee resolved under Section 50(A)(4) of the Local Government (Scotland) Act 1973 that the press and public be excluded from the meeting for the undernoted item of business on the grounds that it involved the likely disclosure of exempt information as defined in paragraph 6 of Part I of Schedule 7A of the Act.

 

VIII AIRPORT SERVICES

 

After considering Agenda Note AN146-2010 relative to the provision of airport services, the Committee approved the recommendation detailed therein.

 

 

 

 

Ken GUILD, Convener.

 

APPENDIX I

 

 

Project/Applicant

Description of Project

Forum Decision Amount

Clepington Gardens and

Allotment Association

 

Replacement of perimeter fencing.

10,000

Brooksbank Centre and Services

To upgrade CCTV facilities in building.

 

900

Douglas Festival Group

To install a permanent power supply to the Douglas Village Green.

 

1,714

63rd Rainbow Guides

To enable group to purchase equipment and attend pantomime.

 

400

Boomerang Mother and Toddlers

To replace worn play mats.

 

273

Wild Wifiezs

To cover the cost of an art project involving 15 women, making a mosaic to display within St Mary's Community Facility.

 

680

St Mary's Toddler Group

A winter outing to the Caledonia Railway in Brechin for 49 adults and children - travel and admission.

 

443

Ardler Family Support Centre

(Social Work)

To fund additional group activities for a 15 parents and 20 children currently supported by Ardler Family Support Centre to promote integration.

850

Ardler Woodland Project

(Leisure and Communities)

To improve the quality of the community woodland areas around Ardler Village.

 

2,412